2007
WinterInstallation of new skylights in the 1916 building is completed.
SpringConstruction begins on the expansion of the museum's parking garage. When completed, this will increase the number of parking spaces for visitors to 620.
SummerRestoration of the 1916 building is finished and turned over to the museum for commissioning (the testing of all electrical and mechanical systems) and acclimatization (to ensure that it can maintain a constant temperature and humidity).
Construction is completed on the east wing, which is turned over to the museum for commissioning and acclimatization.
FallGarage expansion is completed in October; construction begins on the renovation of Gartner Auditorium.